City Funded Housing Projects

3600 San Pablo Avenue (Nellie Hannon Gateway) 

Project Status: Under Construction; Pre-Leasing

Project Description: New construction of 90 residential housing units and 5,900 sq ft of ground floor commercial space for Emeryville Citizen Assistance Program (ECAP). 45 of the units are set-aside as permanent supportive housing for formerly unhoused individuals. 

Developer: Resources for Community Development

Property Manager: John Stewart Company

General Contractor: 

City Investment: $16,747,486

 Unity Type & Income Mix

Income Category

Studio

One Bedroom

Two Bedroom

Three Bedroom

Total

*Special Needs Units

0-20% AMI

27

18

0

0

45

45

21-50% AMI

0

0

6

2

8

0

51-60% AMI

0

24

9

3

36

0

Manager Unit

0

0

1

0

1

0

Total

27

42

16

5

90

45

* Special Needs Units are set-aside for formerly unhoused individuals and families.

Proposed Development Timeline
  • Entitlement Approved: October 2021
  • Close Financing: April 2023
  • Start Construction: June 2023
  • Pre-Leasing: June 2025
  • Complete Construction: September 2025 (Projected)

4300 San Pablo Avenue (Intergeneration Housing Project)

Project Status: Seeking Financing

Project Description: New construction of 68 residential rental housing units for seniors and transitional aged youth (TAY). 13 of the units are set-aside for permanent supportive housing for TAY.

Developer: EAH Housing

Property Manager: EAH Housing

General Contractor: TBD

City Investment: $16,747,486

Unit Type & Income Mix

Income Category

Studio

One Bedroom

Two Bedroom

Total Units

Special Needs: Seniors 

Special Needs:
TAY

0-80% AMI

44

 15 7

67

 54  13

Manager Unit

0

0

1

1

 0  0

Total

44

15

8

68

 54  13

 

Proposed Development Timeline

  • Entitlement Approved: December 2022
  • Close Financing: October 2026 (Projected)
  • Complete Construction: December 2028 (Projected)

5890, 5900, and 6150 Christie Avenue (Perennial Apartments)

Project Status: Seeking Financing

Project Description: New construction of no fewer than 362 affordable family residential units targeted to households with incomes between 30% and 80% of area median income. The Development is expected to be developed in three Phases and include an expansion of Christie Park, an afterschool space, and retail space.

  • Phase 1(Astrid): Approximately 126 residential units, the expansion of Christie Park, childcare or after school space within the building, and retail space of approximately 1,500 square feet.
  • Phase 2 (Bluebell):  Approximately 132 residential units
  • Phase 3 (Clover): Approximately 104 residential units

Developer: EAH Housing

Property Manager: EAH Housing

General Contractor: TBD

City Investment: $23,660,000

 Unit Type Per Development Phase

 Development Phase Studio  One
Bedroom
 
Two
Bedroom
 
Three
Bedroom
 
Total
Phase 1: Astrid   12  27  52 35  126
Phase 2: Bluebell  14  41  42 35  132
Phase 3: Clover  14  27  36 27  104
Total  40  95  130  97  362

 

 Development Income Mix Proposed
0-30% AMI   103
31-40% AMI  72
41-50% AMI  89
51-60% AMI  95
Manager's Unit  3
 Total Units  362

 

Proposed Development Timeline
  • Entitlement Approved: June 2025
  • Phase 1 Close Financing: January 2026 (Projected)
  • Phase 1 Complete Construction: January 2028 (Projected)
  • Phase 2 Close Financing: January 2027 (Projected)
  • Phase 2 Complete Construction: January 2029 (Projected)
  • Phase 3 Close Financing: January 2028 (Projected)
  • Phase 3 Complete Construction: January 2030 (Projected)