Project Status: Under Construction; Pre-Leasing
Project Description: New construction of 90 residential housing units and 5,900 sq ft of ground floor commercial space for Emeryville Citizen Assistance Program (ECAP). 45 of the units are set-aside as permanent supportive housing for formerly unhoused individuals.
Developer: Resources for Community Development
Property Manager: John Stewart Company
General Contractor:
City Investment: $16,747,486
Unity Type & Income Mix
|
Income Category
|
Studio
|
One Bedroom
|
Two Bedroom
|
Three Bedroom
|
Total
|
*Special Needs Units
|
0-20% AMI
|
27
|
18
|
0
|
0
|
45
|
45
|
21-50% AMI
|
0
|
0
|
6
|
2
|
8
|
0
|
51-60% AMI
|
0
|
24
|
9
|
3
|
36
|
0
|
Manager Unit
|
0
|
0
|
1
|
0
|
1
|
0
|
Total
|
27
|
42
|
16
|
5
|
90
|
45
|
* Special Needs Units are set-aside for formerly unhoused individuals and families.
Proposed Development Timeline
- Entitlement Approved: October 2021
- Close Financing: April 2023
- Start Construction: June 2023
- Pre-Leasing: June 2025
- Complete Construction: September 2025 (Projected)
Project Status: Seeking Financing
Project Description: New construction of 68 residential rental housing units for seniors and transitional aged youth (TAY). 13 of the units are set-aside for permanent supportive housing for TAY.
Developer: EAH Housing
Property Manager: EAH Housing
General Contractor: TBD
City Investment: $16,747,486
Unit Type & Income Mix
|
Income Category
|
Studio
|
One Bedroom
|
Two Bedroom
|
Total Units
|
Special Needs: Seniors
|
Special Needs:
TAY
|
0-80% AMI
|
44
|
15 |
7 |
67
|
54 |
13 |
Manager Unit
|
0
|
0
|
1
|
1
|
0 |
0 |
Total
|
44
|
15
|
8
|
68
|
54 |
13 |
Proposed Development Timeline
- Entitlement Approved: December 2022
- Close Financing: October 2026 (Projected)
- Complete Construction: December 2028 (Projected)
Project Status: Seeking Financing
Project Description: New construction of no fewer than 362 affordable family residential units targeted to households with incomes between 30% and 80% of area median income. The Development is expected to be developed in three Phases and include an expansion of Christie Park, an afterschool space, and retail space.
- Phase 1(Astrid): Approximately 126 residential units, the expansion of Christie Park, childcare or after school space within the building, and retail space of approximately 1,500 square feet.
- Phase 2 (Bluebell): Approximately 132 residential units
- Phase 3 (Clover): Approximately 104 residential units
Developer: EAH Housing
Property Manager: EAH Housing
General Contractor: TBD
City Investment: $23,660,000
Unit Type Per Development Phase
|
Development Phase |
Studio |
One
Bedroom |
Two
Bedroom |
Three
Bedroom |
Total |
Phase 1: Astrid |
12 |
27 |
52 |
35 |
126 |
Phase 2: Bluebell |
14 |
41 |
42 |
35 |
132 |
Phase 3: Clover |
14 |
27 |
36 |
27 |
104 |
Total |
40 |
95 |
130 |
97 |
362 |
Development Income Mix Proposed |
0-30% AMI |
103 |
31-40% AMI |
72 |
41-50% AMI |
89 |
51-60% AMI |
95 |
Manager's Unit |
3 |
Total Units |
362 |
Proposed Development Timeline
- Entitlement Approved: June 2025
- Phase 1 Close Financing: January 2026 (Projected)
- Phase 1 Complete Construction: January 2028 (Projected)
-
Phase 2 Close Financing: January 2027 (Projected)
- Phase 2 Complete Construction: January 2029 (Projected)
- Phase 3 Close Financing: January 2028 (Projected)
- Phase 3 Complete Construction: January 2030 (Projected)