Annual Street Rehabilitation and Preventive Maintenance Project

Summer 2018 - Annual Street Rehab Project Information

Public Works is bringing you fresh streets! Be on the lookout for contractor notices 3 days prior to the start of work this August 2018. Approximately one-third of all City streets will be slurry sealed or repaved to improve and maintain pavement quality. Normal construction impacts may include dust, noise, traffic delays and parking restrictions. Project notifications will also be available via the City’s Twitter (@EmeryvilleCA).

Schedule

Completed August 2018

  • August 21 - 24: Telfer Pavement Technologies, LLC finished palm tree removal and did necessary USA alerts for median removal work.

Completed September 2018

  • September 4 - 7: Telfer Pavement Technologies, LLC performed median removal work on Shellmound Street. Temporary paving/striping will remain until separate contractor (De Silva Gates) performs final paving efforts from curb to curb on Shellmound Street at end of September.
  • September 10 - 14: Telfer Pavement Technologies, LLC completed preliminary work needed in order to complete slurry seal work on streets throughout town (all red areas of map below)
    • Work included remaining pothole/digout repairs, crack seal/repair, and various other preliminary items before slurry seal is placed.

Tentative Schedule for Week of (September 17th, 2018)

  • September 17 - 21: DeSilva Gates Construction will begin work on Shellmound Street from the 40th Street Bridge to Shellmound Way. 
    • Contractor will take the lane as needed NB/SB on Shellmound Street, but will always maintain one lane in each direction.
    • Contractor will adjust and lower all manholes, gate valves and utilities in the roadway.
    • Contractor will do digout repairs for larger potholes or failed pavement areas. Most of these locations are near bus stops and near the median areas.
    • On Thursday, DeSilva Gates Construction will begin Grind and Pave work on Shellmound Street from the 40th Street Bridge to Shellmound Way. 
  • September 17 - 21: Telfer Pavement Technologies, LLC will begin slurry seal work throughout City

SepSlurry1

SepSlurry2

SepSlurry3

Tentative Schedule for Week of (September 24th, 2018)

  • September 24 - 28: DeSilva Gates Construction will complete Grind and Pave work on Shellmound Street from the 40th Street Bridge to Shellmound Way. 
    • Contractor plans to do outside lanes first and then do the inside lanes. Access to all driveways/entrances/exits will be maintained throughout the project. Working hours will be 7:00am to 3:30pm
  • September 24 - 28: Telfer Pavement Technologies, LLC will begin striping work in slurry seal work areas throughout City.
    • Schedule to be updated on specific dates that streets will be completed
  • September 27 - 28, and 30th: DeSilva Gates will do night work on Christie Avenue and Powell Street.

Tentative Schedule for Week of (October 1st, 2018)

  • October 1 - 5: DeSilva Gates will finish grind/paving on Christie Avenue and Powell Street.
  • October 1 - 5: Telfer Pavement Technologies, LLC will complete striping work in slurry seal work areas throughout City. 
    • Schedule to be updated on specific dates that streets will be completed